Waterproofing of Basement
Basement waterproofing has assumed lot of importance these days as moist or wet basement could serve as a cause for the proliferation of bacteria, mildew, and mold. Moreover, car parking can also become a mess & affect the overall health & safety of your family. We realize this and have come up with waterproofing solutions which can eradicate such problems.
PROCEDURE FOR BASEMENT (PRE-CONSTRUCTION) WATERPROOFING
- TREATMENT BEFORE CONSTRUCTION OF RCC BASE SLAB OF TANK
- Repair/Smoothen the surface of PCC by 1:4 Cement Sand mortar.
- Apply 2 coats of DURAGARD (cement base polymer/acrylic modified highly flexible waterproof coating). Protect the coating against mechanical damage with 1:4 Cement Sand mortar (admixed with DURA1) of about 15 to 20 mm thickness, as shown in the figure.
- CONCRETING
- Add DURA 1, an integral water proofing compound confirming to IS:2645, shall be added to concrete to reduce permeability and increase the durability. The dosage of DURA 1 is 2% by weight of cement i.e. 1 kg for 50 kg bag of cement.
- DURAKRIT (hardening-cum-bonding agent) shall be used wherever the construction joints are coming. On the existing surface, Cement : Sand slurry shall be applied admixed with DURAKRIT in the ratio Cement : Sand : DURAKRIT mix :: 1:1 : 0.6.The green concrete is placed before the above slurry dries.
- SURFACE PREPARATION
- If honeycombs and voids are found in the retaining wall or slab, grouting has to be done through nozzles fixed at 1 m center-to-center with non-shrinking expansive grout, DURA EV.
- Make the surface free of oil, grease or any loosely adhering particles.
- Repair the substrate with rich mortar and DURAKRIT if there are any cracks (more than 1mm wide), pin holes, honeycombs, etc.
- Round all horizontal and vertical edges by making a mortar gola with rich mortar and DURAKRIT as per the specification of "Mortar Gola".
- TREATMENT AFTER CASTING OF RETAINING WALL & BASE SLAB
- Apply 2 coats of DURAGARD (cement based polymer/acrylic modified highly flexible waterproof coating) from positive side. The second coating must be provided at right angles to first coat once it is touch dry.
- The above treatment shall be provided from outside.
- Water leakage test in full supply level will be carried out as per IS 3370 part 1 for seven days as instructed.
- Protect the coating by laying glazed tiles/cement sand plaster admixed with DURA 1 @ 1 kg for 50 kg bag of cement.